    Post Estimating


    How much detail, if any, do you go into when giving either an estimate or quote to a domestic customer?
    Do you give a breakdown in materials, how much the labour costs and hourly rates, do you agree a price over a handshake, think of a number double it and write it on a business card, scribble it on a notepad or measure precisely and submit a detailed estimate?
    From personal experience I have found that if you give too much information about your estimate to a client, they will use this to shop around for a better price. Anyone else have similar experiences?
    Your messages are really important to us
    ...but not important enough to employ a sufficient number of support staff to answer them.

  2. #2
    Administrator admin's Avatar
    Join Date
    Dec 2008
    Posts
    342
    Thanks
    102
    Thanked 13 Times in 12 Posts

    Default

    That last paragraph made a good point. This post never got a reply, and that's why it's bumped back from the archives.


  3. #3
    VIP TonyM's Avatar
    Join Date
    Jan 2009
    Posts
    1,330
    Thanks
    52
    Thanked 187 Times in 160 Posts

    Default

    Firstly I ask them if they know how many square metres of board there is to tape and what type of house it is. Are there any canopy ceilings or higher than normal bits. If they do, then I multiply it by a rate, add a bit for beads and there's my price. If they say it's a 4 bed house, I say the average 4 bed house is 500 m2 and that'll be x amount. I say that if there's more metres, its going to be a bit more. I'll give them a bang on accurate price if they want it, but if that means going there and measuring up beforehand, that time goes on the quote. I don't let people waste my time. Generally on new build stuff, I don't need to see it before I start.

  4. #4
    Season ticket holder amestaper's Avatar
    Join Date
    Dec 2008
    Location
    Edinburgh
    Posts
    2,601
    Thanks
    423
    Thanked 281 Times in 226 Posts

    Default

    This post must have been buried several pages down? Now I remember sending this after being asked to quote in detail for a house extension and the home owner attempted to haggle a lower price with different permatations.

    Such as;
    they supplied the materials themselves
    they fixed the plasterboard themselves
    suggested I tape the job in 2 quick coats, rather than 3
    what our hourly rate and square metre price was.

    Strange times we're living in when someone else goes around with a tape measure after youve left and calls to let you know your measures a few mm out. Sometimes I feel you're better just getting straight to the point and asking "How low do I need to quote to get this job, and I'll tell you in 10 seconds whether or not I can match the price that Marek Underkunttz has given you!!!"

    In the end up I lost around 3 hours pricing a job I never had a hope in hell of getting. Like Tony I dont have this timewasting hassle on new build. Haste ye back boom times!

    Getting back to why I posted in the first place. I avoid a detailed estimate, and if possible, try to give a fixed price instead.
    Your messages are really important to us
    ...but not important enough to employ a sufficient number of support staff to answer them.

  5. #5
    Member Lightrock's Avatar
    Join Date
    Feb 2009
    Location
    Edmonton Alberta, Canada
    Posts
    86
    Thanks
    8
    Thanked 16 Times in 15 Posts

    Default well it depends

    For small basements, which is the majority of my work this year, I walk down the stairs and add hundreds of dollars until I reach a total which makes me feel good about the job, usually about 1200 - 1800. if i worked that out to hours it would be expensive... about 80/hr. A few years ago Financial Planner whose office I did for told me: "I took your 40$/hr because I trust you, and this $280 is a fair price, but usually a business person would rather hear 400$ than 40/hr and not know the total" I have taken that to heart.
    for contractors I get repeat work from, I have a sliding scale. For each corner bead profile 1.50/' square, 2.50/' for bull-nose and a board price by ceiling height, so a room with an 8' ceiling is 35 cents/ft, a 9 foot ceiling is 40 cents/ft and 10'... goes up from there.

    so my repeat contractors get a pretty detailed quote, casual jobs get a flat rate, and a discount later if I inconvenienced them some how.
    Plumb and Level are the framer's perogative ...I can give you flat and straight... www.lightrocktaping.com

  6. #6
    Season ticket holder amestaper's Avatar
    Join Date
    Dec 2008
    Location
    Edinburgh
    Posts
    2,601
    Thanks
    423
    Thanked 281 Times in 226 Posts

    Default

    10.76 sq ft = 1 sq metre. I had to work that one out LOL.
    Your messages are really important to us
    ...but not important enough to employ a sufficient number of support staff to answer them.

  7. #7
    Member Lightrock's Avatar
    Join Date
    Feb 2009
    Location
    Edmonton Alberta, Canada
    Posts
    86
    Thanks
    8
    Thanked 16 Times in 15 Posts

    Default canada isn't fluent in metric, its broken like our engrish eh

    yeah.. it's a weird country. we adopted the metric system in .. 80? 81? but we still think of mileage for cars in miles per gallon, our height in feet and inches, and all building materials are based on 4x 8 foot sheets and square foot measurements.. which we faithfully transfer to Mils:
    "ceiling height is 1200 mils".
    "What?"
    "um.. about 10 feet I think"
    Plumb and Level are the framer's perogative ...I can give you flat and straight... www.lightrocktaping.com

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. Estimating software enquiry
    By amestaper in forum Business, marketing, and advertising
    Replies: 10
    Last Post: 03-12-2010, 04:36 PM

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •